Relocated Plant Outfall

Traversing through American Cyanamid Superfund site; 4,200 LF of 72″ PCCP gravity outfall pipe and precast structures, 450 CY of CIP concrete structures, 75 LF of 42″ jack and bore water main crossing, 1,136 SY of concrete slabs, 10,500 CY of low permeability backfill, 10,600 CY of excavation of contaminated and hazardous soil, electrical and landscaping work.

Client
Somerset Raritan Valley Sewerage Authority
Value
$9,778,750


OtherProjects

Jersey Shore Outlets Route 66 Overpass and Victoria Blvd

Previous Project

Route 30 Cooper River Drainage

Next Project